V / A = q’ Nq Sq + 0.5 ?’ B’ N? S?
? = q B (1 - ?2) Is / E
Consider a 0.9m diameter pile 25m long (contract pile tests will be done):
Now: max pile load = 0.25 fcu A or fcu =(3500 / 0.64) x 4 =21875 kPa ( e.g use C30 concrete)
Check settlement using equivalent raft: